  "checkedOn": "2026-11-29",
  "projects": [
    {
      "id": "perur-desalination",
      "name": "Perur seawater desalination plant",
      "location": "Chennai metropolitan area, Tamil Nadu",
      "sector": "Desalination",
      "stage": "Construction commenced",
      "owner": "Chennai Metropolitan Water Supply and Sewerage Board",
      "scope": "A 400 MLD design capacity plus pumping, storage, transmission and distribution works.",
      "funding": "JICA ODA loans of ¥30.000 billion (2018) and up to ¥52.556 billion (2025). These are loans for project phases, not a construction contract value.",
      "timeline": [
        {"date":"2018-03","event":"JICA records the first loan agreement for ¥30.000 billion.","source":0},
        {"date":"2023-08-21","event":"JICA announced that construction had commenced.","source":1},
        {"date":"2025-03-27","event":"JICA signed the second loan agreement. Its schedule listed March 2028 as planned commissioning.","source":2}
      ],
      "analysis": "The plant is one part of the delivery system. A commissioning milestone tells readers more when it covers the transmission main and receiving network as well as the plant.",
      "watch": "An updated commissioning schedule and evidence of delivery into the distribution network.",
      "sources": [
        {"name":"JICA phase I project profile","url":"https://www.jica.go.jp/oda/project/ID-P267/"},
        {"name":"JICA construction commencement release","url":"https://www.jica.go.jp/english/overseas/india/information/press/2023/1540578_16802.html"},
        {"name":"JICA phase II loan agreement and schedule","url":"https://www.jica.go.jp/english/information/press/2024/20250327_11.html"}
      ]
    },
    {
      "id": "bengaluru-water-security",
      "name": "Karnataka Water Security and Resilience Program",
      "location": "Bengaluru, Karnataka",
      "sector": "Wastewater and resilience",
      "stage": "Implementation reporting",
      "owner": "Government of Karnataka and participating agencies",
      "scope": "The World Bank approval describes nine sewage treatment plants, lake restoration, sewer connections and reuse.",
      "funding": "US$426 million IBRD loan approved in June 2025. It funds a programme with multiple components.",
      "timeline": [
        {"date":"2025-06-23","event":"The World Bank board approved the program.","source":0},
        {"date":"2026-09","event":"The World Bank published an implementation and results report for project P506272.","source":1}
      ],
      "analysis": "Programme approval is an early signal for suppliers. Opportunities become actionable at the package level, and reuse depends on collection networks and reliable delivery to users.",
      "watch": "Package-level procurement, industrial reuse arrangements and measured volumes delivered.",
      "sources": [
        {"name":"World Bank approval and loan terms","url":"https://www.worldbank.org/en/news/press-release/2025/06/24/new-world-bank-program-to-improve-water-security-for-over-4-million-people-in-india-s-tech-hub-bengaluru"},
        {"name":"World Bank implementation and results report","url":"https://documents.worldbank.org/en/publication/documents-reports/documentdetail/099092426101026253"}
      ]
    },
    {
      "id": "champawat-water-supply",
      "name": "Champawat water supply package",
      "location": "Champawat, Uttarakhand",
      "sector": "Drinking water",
      "stage": "Contract listed by ADB",
      "owner": "Government of Uttarakhand",
      "scope": "ADB lists a 3.5 MLD treatment plant within a water supply package that includes 18 years of operation and maintenance.",
      "funding": "Part of the ADB-backed Uttarakhand Livability Improvement Project. ADB approved a US$200 million loan for the wider multi-sector project, not this package alone.",
      "timeline": [
        {"date":"2024-10-23","event":"ADB announced approval of the wider project loan.","source":0},
        {"date":"2024-12-06","event":"ADB lists the Champawat water supply contract under loan 4510.","source":1}
      ],
      "analysis": "The operating term is a material part of what is being procured. Compare supplier requirements and costs against the complete package scope, including operations.",
      "watch": "Commissioning, service reliability and lifecycle performance.",
      "sources": [
        {"name":"ADB funding approval","url":"https://www.adb.org/news/adb-approves-200-million-loan-enhance-livability-uttarakhand-india"},
        {"name":"ADB project and contract records","url":"https://www.adb.org/projects/56304-001/main"}
      ]
    },
    {
      "id": "siliguri-mahananda-sewage",
      "name": "Siliguri Mahananda sewage interception and treatment",
      "location": "Siliguri, West Bengal",
      "sector": "Wastewater",
      "stage": "Sanction reported",
      "owner": "National Mission for Clean Ganga programme",
      "scope": "Interception and diversion works and sewage treatment for pollution abatement in the Mahananda.",
      "funding": "₹361.86 crore estimated project cost, sanctioned under hybrid annuity PPP mode. The estimate does not establish the contract or amount disbursed.",
      "timeline": [
        {"date":"2025-12-08","event":"The government reported that NMCG had sanctioned the project under hybrid annuity PPP mode.","source":0}
      ],
      "analysis": "Interception and diversion are part of the outcome. Even a commissioned treatment plant cannot treat flows that are not captured and conveyed to it.",
      "watch": "Procurement award, concession milestones and operating results.",
      "sources": [
        {"name":"Government programme statement and sanctioned estimate","url":"https://www.pib.gov.in/PressReleseDetailm.aspx?PRID=2200355&lang=2&reg=3"}
      ]
    }
  ]
}