Perur seawater desalination plant

A 400 MLD design capacity plus pumping, storage, transmission and distribution works.

← All projects · Sources checked

Location
Chennai metropolitan area, Tamil Nadu
Project agency
Chennai Metropolitan Water Supply and Sewerage Board
Latest documented stage
Construction commenced
Scope
A 400 MLD design capacity plus pumping, storage, transmission and distribution works.
Financing
JICA ODA loans of ¥30.000 billion (2018) and up to ¥52.556 billion (2025). These are loans for project phases, not a construction contract value.

Documented timeline

  1. · JICA records the first loan agreement for ¥30.000 billion. Source 1
  2. · JICA announced that construction had commenced. Source 2
  3. · JICA signed the second loan agreement. Its schedule listed March 2028 as planned commissioning. Source 3

WaterBrief analysis

The plant is one part of the delivery system. A commissioning milestone tells readers more when it covers the transmission main and receiving network as well as the plant.

Watch next · An updated commissioning schedule and evidence of delivery into the distribution network.

Sources

  1. JICA phase I project profile
  2. JICA construction commencement release
  3. JICA phase II loan agreement and schedule

This timeline records published milestones. Check the original source before acting on a tender or schedule.

Subscribe to WaterBrief →