Honolulu's Kalaeloa Seawater Desalination Plant Clears Key Approvals, but Construction Start Slips to 2027

Consolidated Water says state heritage and health approvals and a $109m EPA WIFIA loan are in hand for the 1.7 MGD reverse osmosis plant, yet remaining permits push groundbreaking to the first half of 2027.

In brief

Consolidated Water announced on 21 October 2026 that the Kalaeloa Seawater Desalination Facility in western Oahu has secured approvals from Hawaii's State Historic Preservation Division and Department of Health, following a $109 million EPA WIFIA loan to the Honolulu Board of Water Supply. Construction is now expected to begin in the first half of 2027 rather than late 2026, because a heritage agreement and other permits remain outstanding.

The Kalaeloa plant will sit on a 20-acre Board of Water Supply site in Campbell Industrial Park, on Oahu's western shore. It is designed to deliver a guaranteed 1.7 million gallons per day (about 6,400 m³/day) of drinking water by seawater reverse osmosis, with a permitted production range up to 2.55 MGD.

1.7 MGDGuaranteed potable output of the Kalaeloa SWRO plant (about 6,400 m³/day)

What was approved

Consolidated Water's 21 October update lists three milestones. The Hawaii State Historic Preservation Division approved a Preservation Plan and an Archaeological Monitoring Plan. The Department of Health approved a substantial modification of the BWS public water system that will receive the desalinated water. And on 16 October the EPA announced a $109 million WIFIA loan, roughly 49% of $222 million in eligible project costs, which is the maximum share WIFIA allows.

The utility had already issued a limited notice to proceed worth about $6 million in July 2026 so that long-lead equipment could be ordered. A Memorandum of Agreement with the heritage division and other permits are still outstanding.

A slipping schedule

The design-build-operate contract was signed in June 2023. In May 2025 the company expected construction to begin in early 2026; it now expects the first half of 2027. Once commissioned, the plant is to be operated for 20 years, with two optional five-year extensions. The design-build phase is valued at nearly $150 million over 44 months, with operation at about $2.7 million a year.

Why it matters

Island and coastal utilities are turning to seawater RO as a drought hedge, and Kalaeloa shows that permitting rather than technology is usually what sets the timeline.

Found an error? See the Corrections Policy.