Delhi's Shahdara Drain Interceptor Sewer Is 90% Built but Stalled, DJB Tells NGT; 60 MGD of New Trans-Yamuna STPs Not Yet Tendered

Work has been on hold since the monsoon pending irrigation department permission, and two Yamuna Vihar STP units failed effluent standards in July and August.

In brief

The Delhi Jal Board told the National Green Tribunal in an affidavit filed on 26 October that its interceptor pipeline along the Shahdara drain is 90% complete physically but only 48% financially, and has been stalled since the monsoon, Down To Earth reported on 28 October. New 36 MGD and 24 MGD STPs at Kondli and Jagriti Vihar have cost estimates but no tenders yet.

A key piece of Delhi's plan to stop raw sewage reaching the Yamuna is almost built but has not moved for months. In an additional affidavit filed with the National Green Tribunal on 26 October, the Delhi Jal Board (DJB) said the ductile iron interceptor pipeline along the Shahdara drain is 90% complete physically and 48% complete financially, Down To Earth reported on 28 October. The case is OA No. 274 of 2022, Prem Aggarwal and others versus the Delhi government.

90%Physical progress on the Shahdara drain interceptor pipeline, against 48% financial progress, per the DJB affidavit

Waiting on a permit

The pipeline is meant to trap sewage from the Kanti Nagar and Old Seelampur drains before it reaches the Shahdara drain. Work has been on hold since the monsoon began because of restrictions from the Irrigation and Flood Control Department, and permission to restart is still pending. The DJB expects to finish by 31 December 2026, provided that permission comes.

New treatment capacity is further out

The affidavit lists two proposed STPs for Trans-Yamuna: 36 MGD at Kondli and 24 MGD at Jagriti Vihar, 60 MGD combined. Cost estimates are ready, but tenders have not been invited, and the target is December 2028. At Yamuna Vihar, work orders have been issued for a new 20 MGD plant and for expanding Phase-III from 25 to 55 MGD, both due by December 2027. Of 34 household sewer connection works, eight are done and 26 are in progress.

60 MGDCombined capacity of the proposed Kondli (36 MGD) and Jagriti Vihar (24 MGD) STPs, still awaiting tenders

The filing also cites Delhi Pollution Control Committee results for July and August 2026. The Kondli STPs, Phases I to IV, and Yamuna Vihar Phase-II met discharge standards, while Yamuna Vihar Phase-I and Phase-III did not. For Taj Colony, a low-lying settlement where a gravity sewer is not technically feasible, the Delhi Urban Shelter Improvement Board has been asked for a plan for safe sewage disposal. Down To Earth's report covers the DJB's filing and does not record a fresh tribunal order in the matter.

Why it matters

Delhi's Yamuna clean-up depends on catching drain sewage and treating it to standard. This filing shows both parts slipping: a nearly finished pipeline waiting on a permit, and existing plants that still miss their limits.