The tribunal saw dated, geotagged photos of untreated sewage in a drain reported as completed, and asked for a fresh report within two weeks.
In brief
On 25 November 2026 the National Green Tribunal expressed dissatisfaction with a Delhi Jal Board report giving revised timelines for work on 22 drains. Several projects were only marked work in progress and some plant deadlines had slipped by nearly two years, Down To Earth reported.
The National Green Tribunal (NGT) has told the Delhi Jal Board (DJB) to try again. In an order of 25 November 2026, a bench headed by Justice Prakash Shrivastava said it was not satisfied with the board's report setting out revised timelines for work on 22 drains in the capital, and directed it to file a fresh report within two weeks. Down To Earth summarised the order in its court digest the next day.
What was wrong with the report
The bench observed that the updates on sewage treatment plants (STPs) and decentralised sewage treatment plants, the smaller units placed close to where sewage is produced, were vague. Several projects were simply marked as work in progress without saying how much had been finished. The tribunal also noted that operating deadlines for some plants had been pushed back by nearly two years.
Allegations from the applicant
The applicant's counsel alleged that the board was delaying the projects unnecessarily and asked why contracts earlier tendered as single projects had been split into three or four parts and given to different vendors. Counsel also produced dated, geotagged photographs showing untreated sewage flowing through a drain the board had reported as completed.
The tribunal directed the responsible board official to respond, and warned that legal action could follow if an affidavit turned out to contain false information. The photographs and allegations have not been decided on; the board's answer is awaited.
Further checks
The Delhi Pollution Control Committee was asked to inspect the site, analyse water samples and report before the next hearing on 22 December 2026. The bench also wanted details of a nanobubble treatment plant the board is setting up near Defence Colony: whether it is operating, when it was commissioned and how effective it is, noting that public money is involved.
Same day, another Delhi matter
The digest also records the tribunal taking up illegal borewells on Delhi Development Authority land along the Yamuna floodplains, where it was told that 100 to 200 water tankers, besides tractor-mounted ones, were carrying away groundwater. That matter is listed for 3 January 2027.
Why it matters
A progress report that cannot say how much is done cannot be checked. Site photographs with date and location are becoming a practical way to test official claims.